As columns were casted initially, they manpower team placed the dowels for lintels with adequate Development length (Ld) inside the column and caster the concrete. Later, while constructing the masonry, they casted the lintel by lapping the bars with the projected dowels. Is this the good practice sir?
Lapping the bar in below mentioned fashion is a good practice ? content media